Construction Timeline in Islamabad (2025): From Foundation to Finishing
Building a house in Islamabad or anywhere in Pakistan is an exciting journey, but for most homeowners, one question always comes up: “How long will it take?”
The construction timeline of a house depends on factors such as plot size, design complexity, weather conditions, availability of materials, and the efficiency of your contractor. On average, building a 5 Marla to 1 Kanal house in Islamabad can take anywhere between 5 to 18 months.
In this article, we’ll walk you through the step-by-step construction process in Pakistan, from laying the foundation to finishing touches, so you know what to expect at each stage.
Phase 1: Pre-Construction (Planning & Approvals) – 1 to 2 Months
Before you begin digging, you need to:
- Finalize architectural and structural drawings.
- Get approvals from CDA, RDA, or relevant housing society (like DHA, Bahria Town, or Gulberg).
- Arrange financing and budget estimates.
💡 Tip: In Islamabad, CDA approvals can take longer, so it’s smart to begin paperwork early.
Phase 2: Foundation & Structure – 1 to 2 Months
This stage is all about strength and stability. It includes:
- Excavation of the plot.
- Laying the foundation (including waterproofing where necessary).
- Erection of columns, beams, and roof slabs.
- Basic brickwork and blockwork.
⏱️ In Islamabad, a 5 Marla house foundation and grey structure usually takes 1–2 months, while a 1 Kanal house may take up to 1–2 months due to larger covered areas.
Phase 3: Grey Structure Completion – 1 to 3 Months
This phase makes the house recognizable:
- Wall construction and plastering.
- Roofing and slab casting.
- Installation of plumbing lines, electrical conduits, and sewerage systems.
- Boundary wall and initial flooring.
💡 In areas like Banigala, D-12 or E-11 with rocky soil, excavation and foundation may take longer, slightly delaying this stage.
Phase 4: Finishing Works – 4 to 8 Months
This is where the design vision comes alive. Finishing includes:
- Flooring (tiles, marble, or wooden).
- Doors, windows, and aluminum/wooden frames.
- Kitchen and bathroom fittings.
- False ceilings, lighting, and paintwork.
- Cabinetry and wardrobes.
🔑 The finishing stage is the most time-consuming and cost-intensive. Homeowners often extend this timeline by changing material choices or upgrading to imported fittings.
Phase 5: Final Touches & Handover – 1 Month
- Deep cleaning and polishing.
- External works (driveway, landscaping, gates).
- Safety inspections and utility connections (electricity, SNGPL gas, water supply).
- Final handover to the owner.
Average Construction Timeline in Islamabad (2025)
Plot Size | Average Timeline |
5 Marla | 6– 12 months |
10 Marla | 6– 12 months |
1 Kanal | 12 – 18 months |
Factors That Can Delay Construction in Pakistan
- Weather Conditions – Heavy rains or extreme cold in Islamabad can delay concrete curing and finishing.
- Approval Delays – CDA, DHA, or society NOCs often take longer than expected.
- Material Price Fluctuations – Cement, steel, and tile prices can rise suddenly, causing budget and scheduling issues.
- Labor Strikes or Shortages – Skilled labor availability in Islamabad can affect timelines.
- Owner-Driven Changes – Mid-project design changes add time and cost.
Final Word
In Islamabad, building a house in 2025 takes careful planning, budgeting, and professional supervision. While a 5 Marla home can be completed in around a year, larger houses may take up to 18 months.